How to Ensure a Seamless Workflow in an Alluvial Gold Processing Line? From Ore Washing and Screening to the Separate Transport of Concentrates.

The process involves a trommel to wash and separate gravel, a sluice box to capture heavier particles, and a shaking table for final refinement-a sequence that appears to follow the natural flow of water. In practice, however, there is a critical transition point that is frequently misconfigured during the design phase: the material discharged from the sluice box during standard operation consists of tailings, while the gold-bearing material trapped within the collection medium must be recovered during a cleanup phase-after the feed has been stopped-before it can proceed to the next stage of refinement.
This gravity-based placer gold recovery circuit comprises an excavator for feeding, a hopper, a trommel for washing and screening, a sluice box for capture, and a single-deck 6S shaking table for final concentration. The system effectively separates the bulk processing of raw gravel from the subsequent, smaller-scale treatment of the initial concentrate. Whether this configuration is suitable for a specific ore deposit depends on factors such as gold particle size, the degree of mineral liberation, clay content, and the distribution of gold across various particle-size fractions; it cannot be designed simply by assembling equipment based on generic names alone.
When washing gravel, it is essential to clearly distinguish between the material retained on the screen and the material that passes through it.
An excavator feeds raw material into a hopper, which then delivers it to a rotary washing and screening drum. While the hopper must be capable of absorbing the surges caused by loading, the downstream drum and sluice require a relatively steady flow of material. If a full bucket is dumped in all at once, it can lead to an overly thick material layer, insufficient washing, or a sudden spike in the volume of material passing through the screen; the fact that the front end can accommodate the load does not mean the downstream components can process it effectively.
The rotation of the drum, combined with a water supply, causes the gravel to tumble and break apart, separating it into two streams based on the screen aperture size. Coarse material retained on the screen is discharged from the end of the drum, while the slurry that passes through the screen is directed into a sluice. During inspection, one should check whether the coarse material contains trapped mud or sand, whether the screen surface is clogged, and whether any slurry is spilling or bypassing the intended flow path.
Regarding the coarse material discharged from the screen, determining whether it can be discarded as waste rock requires an assessment of any entrained fine material and its gold content. Gold may remain trapped within unwashed mud clods or exist as relatively coarse particles; one cannot simply assume that material retained on the screen is devoid of gold-proper sampling and analysis are necessary. The screen aperture size and the conditions for washing and breaking up the material should be determined through testing; it is a mistake to apply the same screen aperture size to all types of auriferous gravel deposits.
The trommel screen is connected on-site to a downstream sluice box, with the undersize collection and capture zone positioned sequentially. This illustration is intended to show the relationship between pieces of equipment; it does not represent the specific project parameters or processing targets of this proposal.
The material entering the sluice box is a mineral slurry, from which a preliminary concentrate is recovered.
Once the undersize slurry enters the sluice box, water carries the sand particles along the channel. Certain gold particles and heavy minerals are retained within the capture zone, while the remaining material is discharged from the end. As the preliminary concentrate will still contain other heavy minerals and sand, the volume of dark-colored sand observed on the sluice matting should not be equated directly with the amount of gold present.
This process incorporates both sluice-based gravity concentration and gold-capture matting. On-site, it is essential to verify that the channels are clear, that the material flow covers the effective capture area, and that no material is accumulating or obstructing the flow medium. While a "dual-channel" configuration may be visible, this does not imply that the equipment operates via two independent mechanical systems; the specific drive mechanism and operational mode should be verified against the manufacturer's documentation rather than inferred from the name alone.
Fluctuations in clay content, feed rate, or water supply can alter the capture conditions. While increasing the water supply may facilitate material transport, it can also accelerate the loss of fine particles. Before making adjustments, samples should be taken from both the incoming feed and the sluice tailings to determine whether the issue stems from the washing/dispersion stage, the feed rate, or the capture conditions. Simply adding more water whenever sand appears in the tailings is not an appropriate solution.
Cleaning the sluice matting and transporting the concentrate are distinct tasks that require scheduled downtime.
The material sent to the shaking table consists of the preliminary concentrate collected after the feed has been stopped and the sluice cleaned; it is not a matter of simply attaching a pipe to the sluice tailings discharge point. Because capture, cleaning, and transport occur during different operational phases, an arrow on a process flow chart should not be interpreted as a continuous, uninterrupted flow.
During cleaning, the feed to the relevant unit must first be stopped. The water supply, residual material, and capture media must be managed according to the equipment's specific requirements, and the recovered material should be collected in appropriate containers. Capture media must not be disturbed while a large volume of material is still entering from upstream, nor should the material recovered during cleaning be allowed to flow back into the tailings discharge channel. Specific operations must comply with equipment manuals and on-site safety procedures.
For each batch of primary concentrate, the corresponding raw material source and the specific cleanup period must be documented; such batches should be stored and transported separately. Containers, handling equipment, and collection points must be designed to minimize spillage. The choice of containment-whether using drums or other methods-should be determined by the volume of material and the site layout; no single handling method should be assumed as the only viable configuration.
The processing capacity of the entire line must account for the time required for cleanup (clearing material), temporary storage of concentrates, and batch-wise final beneficiation. Since shaking tables process material that has already been enriched, the number of units required cannot be determined simply by applying the raw ore throughput capacity of the preceding drum-based equipment. Conversely, an accumulation of primary concentrate can disrupt both the cleanup process and the operational scheduling of upstream stages. It is necessary to separately calculate the raw ore volume, the yield of primary concentrate, and the actual operating time for each stage.

Material enriched in the sluice is collected separately after the feed is stopped and the sluice mats are cleaned; it is then transported in batches to a single-deck 6S shaking table-the sluice tailings are not fed directly to the shaking table.
During the cleaning process on the single-deck 6S shaking table, it is essential to maintain the distinct identity of the three separate product streams. The preliminary concentrate, once transported to the cleaning area, must be prepared into a suitable feed state. Since the material may have settled-with solids at the bottom and a water layer on top-it should not be dumped onto the table surface all at once. The feed rate, water flow, and material composition must remain relatively stable. The necessary particle size distribution should be determined through ore testing; additional grinding or desliming equipment should not be specified without prior verification.
The shaking table utilizes a reciprocating motion combined with a transverse flow of water to create distinct movement trajectories for particles of varying characteristics, allowing for the separate collection of concentrate, middlings, and tailings based on their respective zones on the table deck. Operating parameters-such as stroke length, stroke frequency, deck slope, and water flow rate-must be tailored to the specific material; recommended settings cannot be derived simply by observing the color of the material on the table or from photographs.
Middlings are collected separately, and their subsequent handling-whether through further processing or other means-is determined by analysis and additional testing; they should not be automatically returned to the primary feed hopper. Direct recycling can lead to an accumulation of material in the circuit and may cause the mixing of streams from different processing stages. During ore testing, all three product streams must be retained, weighed, and sampled; this is the only way to determine whether the cleaning process has successfully increased the grade, or if a portion of the gold has instead been diverted into the middlings or tailings.
Coarse materials, two sections of tailings and water must have their own places to go.
The coarse material on the screen, chute tailings and shaker tailings respectively reflect the effects of screening, washing and dispersion, preliminary capture and selection. When checking the loss, separate samples should be kept before mixing. You cannot just take a sample from the main outlet and then guess at which link the gold was lost. Minerals are intermediate products that need further judgment and should be managed separately from tailings.
Sand-containing water needs to be collected in a controlled manner, and treated and reused according to settlement, mud-containing and water supply conditions. Just because the water looks clear does not mean that it can be returned to any water point; the water quantity, water quality and system mud accumulation should also be checked. The water treatment facilities that have not yet been determined in the process must be completed during the engineering design stage. The words "tailings treatment" cannot be regarded as complete facilities.
The end point is the gold-containing concentrate, and the acceptance must be calculated together with all the materials.
Shaking bed concentrate is still a collection of gold-bearing minerals and is not equal to pure gold, nor can the grade of gold be confirmed solely by bright yellow particles. After centralized collection, numbering, sample retention and testing are required. The subsequent mercury-free recycling method should be determined separately based on the testing results. This route will not connect unconfirmed post-processing equipment until the gold-containing concentrate is ready for inspection.
The same batch of tests should record the raw materials, coarse materials on the screen, chute tailings, shaker fine tailings, and residues in equipment and containers. The preliminary concentrate of the chute is an intermediate material transferred to the shaking table, and cannot be added repeatedly with the shaking table concentrate when calculating the final recovery. Inventory that has not yet been selected should also be listed separately to avoid mistaking temporary storage for losses.
Whether the handover is reliable can come down to several checkable results. The coarse materials are arranged independently, the feed under the sieve is stable, the carpet cleaning products are collected completely, the three products of the shaker are clearly separated, and the sampling records can correspond to the same batch of materials. Only by connecting these links can we have a basis to continue to determine the equipment combination and operation arrangements.